Project: Glanaruddery Windfarm

  • Project: Glanaruddery Windfarm
  • Owner: Impax Asset Management
  • Client: Michael Doyle Civils Engineering
  • Engineer: Natural Power
  • Location: Kerry, Ireland

Electrical Balance of Plant contract for the Glanaruddery 11 X 3.3MW turbine windfarm. Glanaruddery is connected to the existing Cloughboola 110/20kV substation via 7km U/G 20kV cable.

Project Scope

Design and Build contract for the engineering, procurement, construction and commissioning of electrical and civil works to all Impax, ESB Networks and Eirgrid functional specifications including;

  • 2 no. 20kV Siemens NxPlusC Switchboards
  • HV system control, protection, metering, remote annunciation panels and battery systems.
  • 20kV collector circuit cabling
  • Fibre Optic network
  • Complete commissioning of substation and HV cable circuits including VLF testing

Glanaruddery Windfarm

  • Photo of Glanaruddery Windfarm